BJCS MPH Building Plans
 
 
 
 
 
 
 
Multi-Purpose Hall
 
 
Multi-Purpose Hall Update
 
 
Primary School 21st Century (P21) Project - Monday, 21 December 2009

Under the Primary Schools in the 21st Century project (P21), BJCS will be receiving a new Library and Multi-Purpose Hall.

 
Update on the BJCS Multi-Purpose Hall (MPH) - Monday, 21 December 2009

All building licenses have been submitted and council questions have been answered as required.

A check was made at the campus to see that the school complies with current fire regulations for a MPH.  There is enough water and pressure available at this stage, and an application is in progress for a fire hydrant.

The builder expects that from start to finish it will take approx 40 weeks to build all facilities.

We are looking for involvement from the Association, if you are interested in helping out with busy bees etc, please contact your Council representative in the Building Committee (see BER homepage).

 
 
 
 
 
 
 
Photo of site for the future BJCS Multi-Purpose Hall
 
 
Photo of the future site at BJCS - Tuesday, 22 December 2009

 

 
 
 
 
 
 
 
March Update
 
 
Building Approval - Tuesday, 9 March 2010

Planning and building approval had been received from the Shire for the BJCS Sports Hall. 

On Thursday 4th March 2010, the FRSA Board gave official approval for the building of the Sports Hall in Byford to a similiar size as the Halls in Kelmscott and Rockingham. 

Alita Constructsion are making preparations to commence with the construction of the Hall.

 
3D Images of BJCS MPH - Tuesday, 9 March 2010

We have received some 3D visual images of the Sports Halls, which gives us a good idea of how the completed Hall will look.

 
 
 
 
 
 
 
April Update
 
 
28th April 2010 - Wednesday, 28 April 2010

All the columns are almost up as you can see on the below pictures.  It is expected that the tilt panels will be put up within the next few days.

 
BC Meeting: 20th April 2010 - Tuesday, 27 April 2010

The Building C'tee (BC) members met together on 20th April to discuss the updated progress on the MPHs and Libraries.

At the meeting it was reported that the columns and tilt panels for the BJCS MPH would go up in the last week of April.  See below a couple updated photos at BJCS:

It's expected that the MPH will be completed by the end of 2010 D.V.

 
 
 
 
 
 
 
May Update
 
 
Progress photos.... - Thursday, 20 May 2010

The walls are going up in BJCS on the MPH, see below the progres photos....

 
 
 
 
 
 
 
July Udpate
 
 
Updated Photos - Friday, 2 July 2010

 
 
 
 
 
 
 